Hillside Sport Court Park

Hillside Sport Court Playground
Project Status: Construction

Project Overview:

Hillside Sport Court Park is a neighborhood park located in Duluth’s Central Hillside neighborhood. In 2023, Duluth Parks and Recreation conducted an inclusive planning process to establish a renewed vision of the park. The Hillside Sport Court Park Plan was adopted by Duluth City Council on August 21, 2023.

Planned park improvements include: enhancing site connectivity and accessibility, adding a pavilion and picnic area, renewing and expanding the sport court, replacing the playground, maintaining open green space, allotting space for a community garden, improving accessible parking, and repairing or replacing other park assets such as fencing, retaining walls, stairs, bike racks, signage, gate, trees, vegetation, etc.

Project Update:

After a competitive bid process, Rachel Contracting has been selected as the contractor for the park improvement project. Work is expected to begin in June 2026.

Prior to the park improvement project, the City's Public Works and Utilities team will be repairing and replacing sanitary lines within the park. This will include significant earthwork and is expected to take place during the months of April-early June, with the park improvement project to follow.

Funding Source:

Funding sources include grant support from the National Park Service/MN Department of Natural Resources Outdoor Recreation Legacy Partnership Program, and Housing and Urban Development/City of Duluth Community Development Block Grant funds. Additional project support includes City revenue replacement funds and City Park Fund dollars.

Timeline:

Summer 2023: Hillside Sport Court Park Plan is adopted by Duluth City Council.

Fall 2023-Spring 2024: Applications for grant funding to support plan implementation are developed and submitted.

Summer 2024: City received notification of grant awards; Dilapidated building is removed.

Summer 2025: Contracts for grant awards formalized.

Fall 2025: Final design and construction documents are developed.

Winter 2025-2026: Bid documents developed, project bid out and awarded to contractor.

Summer 2026: Utility repairs to be completed; project construction to begin.

Fall 2026: Park improvement project to be completed.

Important Documents:

All documents linked below have been archived and will not be updated. All links open in a new window.

Project Partners:

St. Mark Giving Garden and Food Access Program
Health Equity Northland