2026 Street Preservation Project 2317- Lincoln Park and Spirit Valley- Updates
2026 Street Preservation Project-general comments on work schedule:
For properties with un-permitted private retaining walls, private utilities, lights, gardens, trees, etc. in the Right-of-Way (ROW), it is up to the owner to remove or salvage them for the work and replace them at their own expense. If they are damaged or must be removed for the work, the City will notify owners of the project with a letter and schedule a public meeting to address the work in the ROW before construction. During construction, efforts will be made to notify owners of ROW impacts. If it is covered under a Concurrent Use Permit, then there are similar requirements in that permit.
We will try to maintain mail and garbage service. Coordination with residents and garbage will happen during construction. It is helpful to have your address on your garbage cans in case we have to move them.
We will try to maintain access unless we are pouring your driveway, at which point we will knock on your door and work with you, as we will need to allow about a week to pour your driveway and allow for curing before you can drive on it.
Milling and paving the street will be scheduled once a group of streets have the concrete work completed. The streets will be reposted “No Parking” for each of those operations again. There might be 2-3 week delays in final concrete work and paving so we can have enough streets prepared to make paving cost effective.
August 10, 2026, Update:
Lincoln Park
Restoration this week on these streets:
- W 4th Street (20th Ave. West to 25th Ave. West)
- W 5th Street (TH53 to25th Ave. West)
- 20th Ave. West (3rd to 4th Street)
- 21st Ave. West (3rd Street to 6th Street)
- 22nd Ave. West (3rd to 8th Street)
- 23rd Ave. West (3rd to 5th Street)
Concrete work will continue the week of august 10th on the following streets:
- W 11th Street (TH53 to 22nd Ave. West)
- W 12th Street (TH 53 to dead end east)
- W 13th Street (TH 53 to dead end east)
- 22nd Ave. West (West 11th Street to W 10th Street)
Schedule will be updated on the following streets as the project progresses:
- 34th Ave. West (Grand Ave. to Superior Street)
- Carlton Street (W Superior to Grand Ave.)
- 39th Ave West (Michigan to Superior Street)
- W Superior Street (Carlton to Jenswold)
- Jenswold (W Superior to W Michigan)
- W Michigan Street (Jenswold to 39th)
- W 3rd Street (13th Ave. West to 17th Ave. West)
Spirit Valley
Storm work will start on this street the week of August 10th:
- Wadena Street (Mike Colalillo Dr. to 54th Ave. West)
July 27, 2026, Update:
Lincoln Park:
Paving will be completed this week on these streets:
- W 4th Street (20th Ave. West to 25th Ave. West)
- W 5th Street (TH53 to25th Ave. West)
- 20th Ave. West (3rd to 4th Street)
- 21st Ave. West (3rd Street to 6th Street)
- 22nd Ave. West (3rd to 8th Street)
- 23rd Ave. West (3rd to 5th Street)
Curb and sidewalk work will continue the week of July 27th on the following streets:
- W 11th Street (TH53 to 22nd Ave. West)
- W 12th Street (TH 53 to dead end east)
- W 13th Street (TH 53 to dead end east)
One lift of bituminous will be placed on 22nd this week to help prevent erosion. Final paving will happen when 11th, 12th and 13th are paved:
- 22nd Ave. West (West 11th Street to W 10th Street
Schedule will be updated on the following streets as the project progresses:
- 34th Ave. West (Grand Ave. to Superior Street)
- Carlton Street (W Superior to Grand Ave.)
- 39th Ave West (Michigan to Superior Street)
- W Superior Street (Carlton to Jenswold)
- Jenswold (W Superior to W Michigan)
- W Michigan Street (Jenswold to 39th)
- W 3rd Street (13th Ave. West to 17th Ave. West)
Spirit Valley:
- Wadena Street (Mike Colalillo Dr. to 54th Ave. West)
July 20, 2026, Update:
Lincoln Park:
Concrete will be completed this week. Milling is planned this week also on the following streets:
- W 4th Street (20th Ave. West to 25th Ave. West)
- W 5th Street (TH53 to25th Ave. West)
- 20th Ave. West (3rd to 4th Street)
- 21st Ave. West (3rd Street to 6th Street)
- 22nd Ave. West (3rd to 8th Street)
- 23rd Ave. West (3rd to 5th Street)
Street work on the following streets to continue the week of July 20th with concrete work later in the week for the following streets:
- W 11th Street (TH53 to 22nd Ave. West)
- W 12th Street (TH 53 to dead end east)
- W 13th Street (TH 53 to dead end east)
- 22nd Ave. West (West 11th Street to W 10th Street
Schedule will be updated on the following streets as the project progresses:
- 34th Ave. West (Grand Ave. to Superior Street)
- Carlton Street (W Superior to Grand Ave.)
- 39th Ave West (Michigan to Superior Street)
- W Superior Street (Carlton to Jenswold)
- Jenswold (W Superior to W Michigan)
- W Michigan Street (Jenswold to 39th)
- W 3rd Street (13th Ave. West to 17th Ave. West)
Spirit Valley:
- Wadena Street (Mike Colalillo Dr. to 54th Ave. West)
June 29, 2026, Update:
Lincoln Park:
Concrete removals, storm work and pouring concrete curb and gutters will continue on the following streets:
- W 4th Street (20th Ave. West to 25th Ave. West)
- W 5th Street (TH53 to25th Ave. West)
- 20th Ave. West (3rd to 4th Street)
- 21st Ave. West (3rd Street to 6th Street)
- 22nd Ave. West (3rd to 8th Street)
- 23rd Ave. West (3rd to 5th Street)
Street work on the following street planned to be starting the week of July 13th:
- W 11th Street (TH53 to 22nd Ave. West)
- W 12th Street (TH 53 to dead end east)
- W 13th Street (TH 53 to dead end east)
- 22nd Ave. West (West 11th Street to W 10th Street
Schedule will be updated on the following streets as the project progresses:
- 34th Ave. West (Grand Ave. to Superior Street)
- Carlton Street (W Superior to Grand Ave.)
- 39th Ave West (Michigan to Superior Street)
- W Superior Street (Carlton to Jenswold)
- Jenswold (W Superior to W Michigan)
- W Michigan Street (Jenswold to 39th)
- W 3rd Street (13th Ave. West to 17th Ave. West)
Spirit Valley
Schedule will be updated on the following streets as the project progresses:
- Wadena Street (Mike Colalillo Dr. to 54th Ave. West)
June 22, 2026, Update:
Lincoln Park:
Concrete removals, storm work, and pouring concrete curb and gutters will continue on the following streets:
- West 4th Street (20th Avenue West to 25th Avenue West)
- West 5th Street (TH53 to 25th Avenue West)
- 20th Avenue West (3rd to 4th Street)
Removals will be starting on the avenues the week of the 22nd also for these streets:
- 21st Avenue West (3rd Street to 6th Street)
- 22nd Avenue West (3rd to 8th Street)
- 23rd Avenue West (3rd to 5th Street)
Schedule will be updated on the following streets as the project progresses:
- 34th Avenue West (Grand Avenue to Superior Street)
- Carlton Street (West Superior to Grand Avenue)
- 39th Ave West (Michigan to Superior Street)
- West Superior Street (Carlton to Jenswold)
- Jenswold (West Superior to West Michigan)
- West Michigan Street (Jenswold to 39th)
- West 11th Street (TH53 to 22nd Avenue West)
- West 12th Street (TH 53 to dead end east)
- West 13th Street (TH 53 to dead end east)
- 22nd Avenue West (West 11th Street to West 10th Street
- West 3rd Street (13th Avenue West to 17th Avenue West)
Spirit Valley:
- Wadena Street (Mike Colalillo Drive to 54th Avenue West)
June 8, 2026, Update:
Lincoln Park:
Concrete removals, storm work and pouring concrete curb and gutters will continue on the following streets:
- West 4th Street (20th Avenue West to 25th Avenue West)
- West 5th Street (TH53 to 25th Avenue West)
- 20th Avenue West (3rd to 4th Street)
Schedule will be updated on the following streets as the project progresses:
- 34th Avenue West (Grand Avenue to Superior Street)
- Carlton Street (West Superior to Grand Ave.)
- 39th Avenue West (Michigan to Superior Street)
- West Superior Street (Carlton to Jenswold)
- Jenswold (West Superior to West Michigan)
- West Michigan Street (Jenswold to 39th)
- 21st Avenue West (3rd Street to 6th Street)
- West 5th Street (TH53 to 25th Avenue West)
- 22nd Avenue West (3rd to 8th Street)
- 23rd Avenue West (3rd to 5th Street)
- West 11th Street (TH53 to 22nd Avenue West)
- West 12th Street (TH 53 to dead end east)
- West 13th Street (TH 53 to dead end east)
- 22nd Avenue West (West 11th Street to West 10th Street
- West 3rd Street (13th Avenue West to 17th Avenue West)
Spirit Valley
Schedule will be updated on the following streets as the project progresses:
- Wadena Street (Mike Colalillo Drive to 54th Avenue West)
June 1, 2026, Update:
Lincoln Park:
Storm work will continue along with concrete removals (concrete curb and gutter and driveways) on the following streets:
- West 4th Street (20th Avenue West to 25th Avenue West)
- 20th Avenue West (3rd to 4th Street)
Schedule will be updated on the following streets as the project progresses:
- 34th Avenue West (Grand Avenue to Superior Street)
- Carlton Street (West Superior Street to Grand Avenue)
- 39th Avenue West (Michigan to Superior Street)
- West Superior Street (Carlton to Jenswold)
- Jenswold Street (West Superior Street to West Michigan Street)
- West Michigan Street (Jenswold Street to 39th Avenue West)
- 21st Avenue West (3rd Street to 6th Street)
- West 5th Street (TH53 to25th Avenue West)
- 22nd Avenue West (3rd to 8th Street)
- 23rd Avenue West (3rd to 5th Street)
- West 11th Street (TH53 to 22nd Avenue West)
- West 12th Street (TH 53 to dead end east)
- West 13th Street (TH 53 to dead end east)
- 22nd Avenue West (West 11th Street to W 10th Street
- West 3rd Street (13th Avenue West to 17th Avenue West)
Spirit Valley:
Schedule will be updated on the following street as the project progresses:
- Wadena Street (Mike Colalillo Drive to 54th Avenue West)