2026 Street Preservation Project 2255- Morley Heights- Weekly Updates

2026 Street Preservation Project-general comments on work schedule:

We will try to maintain mail and garbage service.
We will try to maintain access unless we are pouring your driveway, at which point we will knock on your door and work with you as we will need to allow about a week to pour your driveway and allow for curing before you can drive on it.
Milling and paving the street will be scheduled once a group of streets have the concrete work completed. The streets will be reposted “No Parking” for each of those operations again.


Week of June 8, 2026:

Morley Heights:

Work is planned to start on Everett Street the week of June 8th. Reclamation of the street is scheduled for Thursday June 11th, with storm work starting Monday June 15th.

  • Everett Street

Updates for the following streets will updated as work progresses.

  • Cherie Lane
  • Woodbury Lane
  • Jill Street

Week of June 1, 2026:

Morley Heights:

Work is planned to start on Everett Street mid-June. There will be an update to schedule the week before.

  • Everett Street
  • Cherie Lane
  • Woodbury Lane
  • Jill Street