2026 Street Preservation Project 2092- Gary New Duluth, Duluth Heights, Chester Park, and UMD- Updates


2026 Street Preservation Project-general comments on work schedule:

We will try to maintain mail and garbage service.
We will try to maintain access unless we are pouring your driveway, at which point we will knock on your door and work with you as we will need to allow about a week to pour your driveway and allow for curing before you can drive on it.
Milling and paving the street will be scheduled once a group of streets have the concrete work completed. The streets will be reposted “No Parking” for each of those operations again.


July 27th, 2026 update:

Gary-New Duluth:

Storm work will continue the week of the 25thth along with concrete removals (concrete curb and gutter and driveways).

  • Gary Street - restoration and striping left.
  • W Dickson Street – waiting for a storm structure at the creek crossing, once that is installed, paving can be completed.
  • Hudson Boulevard - completed – Restoration remaining.

Duluth Heights:

The watermain replacement project is completed. Reclaiming the week of July 27th:

  • Chambersburg Ave

Kenwood:

No start date scheduled for 13th yet.

  • E 13th Street

Lowering manhole and removals continuing the week of July 20th. Concrete removals, storm repairs and reclaiming will happen the week of July 27th for the following streets:

  • Fern Ave.
  • Martha Street
  • Howtz Ave.
  • Cliff Ave.
  • Hawkins Street
  • Boulevard Place

Chester Park-UMD:

Manhole lowering and reclaiming the week of July 27th:

  • Elizabeth Street

July 20th, 2026 update:

Gary-New Duluth:

Storm work will continue the week of the 25thth along with concrete removals (concrete curb and gutter and driveways):

  • Gary Street - restoration and striping left.
  • W Dickson Street – waiting for a storm structure at the creek crossing, once that is installed, paving can be completed.
  • Hudson Boulevard - completed – Restoration remaining.

Duluth Heights:

The watermain replacement project is completed. Reclaiming the week of July 27th:

  • Chambersburg Ave

Kenwood:

No start date scheduled for 13th yet:

  • E 13th Street

Lowering manhole and removals continuing the week of July 20th. Reclaiming will happen the week of the July 27th for the following streets:

  • Fern Ave.
  • Martha Street
  • Howtz Ave.
  • Cliff Ave.
  • Hawkins Street
  • Boulevard Place

Chester Park-UMD:

No start date scheduled for following street:

  • Elizabeth Street

June 29, 2026 update:

Gary-New Duluth:

Storm work will continue the week of the 25th along with concrete removals (concrete curb and gutter, and driveways).

  • Gary Street
  • West Dickson Street (will follow Gary)
  • Hudson Boulevard (completed until reclamation process in a few weeks)

Duluth Heights:

The watermain replacement project is completed. The street is a few weeks out.

  • Chambersburg Avenue

Kenwood:

No start date scheduled for 13th yet:

  • East 13th Street

Lowering manhole and removals continuing the week of June 29th for the following streets:

  • Fern Avenue
  • Martha Street
  • Howtz Avenue
  • Cliff Avenue
  • Hawkins Street
  • Boulevard Place

Chester Park-UMD:

No start date scheduled for the following street:

  • Elizabeth Street

June 22, 2026 update:

Gary-New Duluth:

Storm work will continue the week of the 25th along with concrete removals (concrete curb and gutter and driveways).

  • Gary Street
  • West Dickson Street (will follow Gary)
  • Hudson Boulevard (completed until reclamation process in a few weeks).

Duluth Heights:

The watermain replacement project is scheduled to be completed by end of June and then street work will begin.

  • Chambersburg Avenue

Kenwood:

No start date scheduled for 13th yet.

  • East 13th Street

Lowering manhole and removals possibly starting the week of June 22nd for the following streets:

  • Fern Avenue
  • Martha Street
  • Howtz Avenue
  • Cliff Avenue
  • Hawkins Street
  • Boulevard Place

Chester Park-UMD:

No start date scheduled for following street:

  • Elizabeth Street

June 8, 2026 update:

Gary-New Duluth:

Storm work will continue the week of the 25th along with concrete removals (concrete curb and gutter and driveways).

  • Gary Street
  • West Dickson Street (will follow Gary)
  • Hudson Boulevard (completed until reclamation process in a few weeks).

Duluth Heights:

The watermain replacement project is scheduled to be completed by end of June and then street work will begin.

  • Chambersburg Avenue

Kenwood:

Once project is up and running will post schedule for following streets:

  • East 13th Street
  • Fern Avenue
  • Martha Street
  • Howtz Avenue
  • Cliff Avenue
  • Hawkins Street
  • Boulevard Place

Chester Park-UMD:

Once project is up and running will post schedule for following street:

  • Elizabeth Street

June 1, 2026 update:

Gary-New Duluth:

Storm work will continue along with concrete removals (concrete curb and gutter and driveways).

  • Gary Street
  • W Dickson Street (will follow after Gary)
  • Hudson Boulevard (completed until reclamation process in a few weeks)

Duluth Heights:

The watermain replacement project is scheduled to be completed by end of June and then street work will begin.

  • Chambersburg Ave

Kenwood:

Once project is up and running will post schedule for following streets:

  • East 13th Street
  • Fern Avenue
  • Martha Street
  • Howtz Avenue
  • Cliff Avenue
  • Hawkins Street
  • Boulevard Place

Chester Park/UMD:

Once project is up and running will post schedule for following street:

  • Elizabeth Street

May 18, 2026 update:

No changes from last week.


May 11, 2026 update:

Gary-New Duluth:

Storm Work will start week of 11th along with concrete removals (concrete curb and gutter and driveways):

  • Gary Street
  • West Dickson Street
  • Hudson Boulevard

Duluth Heights:

The watermain replacement project will be completed by end of June and then street work will begin:

  • Chambersburg Avenue

Kenwood:

Once project is up and running will post schedule for following streets:

  • East 13th Street
  • Fern Avenue
  • Martha Street
  • Howtz Avenue
  • Cliff Avenue
  • Hawkins Street
  • Boulevard Place

Chester Park-UMD:

Once project is up and running will post schedule for following street:

  • Elizabeth Street