2026 Street Preservation Project 2092- Gary New Duluth, Duluth Heights, Chester Park, and UMD- Updates
2026 Street Preservation Project-general comments on work schedule:
For properties with un-permitted private retaining walls, private utilities, lights, gardens, trees, etc. in the Right-of-Way (ROW), it is up to the owner to remove or salvage them for the work and replace them at their own expense. If they are damaged or must be removed for the work, the City will notify owners of the project with a letter and schedule a public meeting to address the work in the ROW before construction. During construction, efforts will be made to notify owners of ROW impacts. If it is covered under a Concurrent Use Permit, then there are similar requirements in that permit.
We will try to maintain mail and garbage service. Coordination with residents and garbage will happen during construction. It is helpful to have your address on your garbage cans in case we have to move them.
We will try to maintain access unless we are pouring your driveway, at which point we will knock on your door and work with you, as we will need to allow about a week to pour your driveway and allow for curing before you can drive on it.
Milling and paving the street will be scheduled once a group of streets have the concrete work completed. The streets will be reposted “No Parking” for each of those operations again. There might be 2-3 week delays in final concrete work and paving so we can have enough streets prepared to make paving cost effective.
August 10, 2026, Update:
Gary-New Duluth
Storm work will continue, along with concrete removals (concrete curb and gutter, and driveways).
- Gary Street – Restoration to complete.
- W Dickson Street –milling and paving in the next few weeks.
- Hudson Boulevard - completed – Restoration remaining.
Duluth Heights
Driveway culverts and storm the week of August 10th:
- Chambersburg Ave
Kenwood
No start date scheduled for 13th yet:
- E 13th Street
Concrete removals, storm repairs will happen the week of August 10th for the following streets:
- Fern Ave.
- Martha Street
- Howtz Ave.
- Cliff Ave.
- Hawkins Street
- Boulevard Place
Chester Park-UMD
Manhole lowering and reclaiming continuing:
- Elizabeth Street
July 27, 2026, Update:
Gary-New Duluth:
Storm work will continue the week of the 25thth along with concrete removals (concrete curb and gutter and driveways).
- Gary Street - restoration and striping left.
- W Dickson Street – waiting for a storm structure at the creek crossing, once that is installed, paving can be completed.
- Hudson Boulevard - completed – Restoration remaining.
Duluth Heights:
The watermain replacement project is completed. Reclaiming the week of July 27th:
- Chambersburg Ave
Kenwood:
No start date scheduled for 13th yet.
- E 13th Street
Lowering manhole and removals continuing the week of July 20th. Concrete removals, storm repairs and reclaiming will happen the week of July 27th for the following streets:
- Fern Ave.
- Martha Street
- Howtz Ave.
- Cliff Ave.
- Hawkins Street
- Boulevard Place
Chester Park-UMD:
Manhole lowering and reclaiming the week of July 27th:
- Elizabeth Street
July 20, 2026, Update:
Gary-New Duluth:
Storm work will continue the week of the 25thth along with concrete removals (concrete curb and gutter and driveways):
- Gary Street - restoration and striping left.
- W Dickson Street – waiting for a storm structure at the creek crossing, once that is installed, paving can be completed.
- Hudson Boulevard - completed – Restoration remaining.
Duluth Heights:
The watermain replacement project is completed. Reclaiming the week of July 27th:
- Chambersburg Ave
Kenwood:
No start date scheduled for 13th yet:
- E 13th Street
Lowering manhole and removals continuing the week of July 20th. Reclaiming will happen the week of the July 27th for the following streets:
- Fern Ave.
- Martha Street
- Howtz Ave.
- Cliff Ave.
- Hawkins Street
- Boulevard Place
Chester Park-UMD:
No start date scheduled for following street:
- Elizabeth Street
June 29, 2026, Update:
Gary-New Duluth:
Storm work will continue the week of the 25th along with concrete removals (concrete curb and gutter, and driveways).
- Gary Street
- West Dickson Street (will follow Gary)
- Hudson Boulevard (completed until reclamation process in a few weeks)
Duluth Heights:
The watermain replacement project is completed. The street is a few weeks out.
- Chambersburg Avenue
Kenwood:
No start date scheduled for 13th yet:
- East 13th Street
Lowering manhole and removals continuing the week of June 29th for the following streets:
- Fern Avenue
- Martha Street
- Howtz Avenue
- Cliff Avenue
- Hawkins Street
- Boulevard Place
Chester Park-UMD:
No start date scheduled for the following street:
- Elizabeth Street
June 22, 2026, Update:
Gary-New Duluth:
Storm work will continue the week of the 25th along with concrete removals (concrete curb and gutter and driveways).
- Gary Street
- West Dickson Street (will follow Gary)
- Hudson Boulevard (completed until reclamation process in a few weeks).
Duluth Heights:
The watermain replacement project is scheduled to be completed by end of June and then street work will begin.
- Chambersburg Avenue
Kenwood:
No start date scheduled for 13th yet.
- East 13th Street
Lowering manhole and removals possibly starting the week of June 22nd for the following streets:
- Fern Avenue
- Martha Street
- Howtz Avenue
- Cliff Avenue
- Hawkins Street
- Boulevard Place
Chester Park-UMD:
No start date scheduled for following street:
- Elizabeth Street
June 8, 2026, Update:
Gary-New Duluth:
Storm work will continue the week of the 25th along with concrete removals (concrete curb and gutter and driveways).
- Gary Street
- West Dickson Street (will follow Gary)
- Hudson Boulevard (completed until reclamation process in a few weeks).
Duluth Heights:
The watermain replacement project is scheduled to be completed by end of June and then street work will begin.
- Chambersburg Avenue
Kenwood:
Once project is up and running will post schedule for following streets:
- East 13th Street
- Fern Avenue
- Martha Street
- Howtz Avenue
- Cliff Avenue
- Hawkins Street
- Boulevard Place
Chester Park-UMD:
Once project is up and running will post schedule for following street:
- Elizabeth Street
June 1, 2026, Update:
Gary-New Duluth:
Storm work will continue along with concrete removals (concrete curb and gutter and driveways).
- Gary Street
- W Dickson Street (will follow after Gary)
- Hudson Boulevard (completed until reclamation process in a few weeks)
Duluth Heights:
The watermain replacement project is scheduled to be completed by end of June and then street work will begin.
- Chambersburg Ave
Kenwood:
Once project is up and running will post schedule for following streets:
- East 13th Street
- Fern Avenue
- Martha Street
- Howtz Avenue
- Cliff Avenue
- Hawkins Street
- Boulevard Place
Chester Park/UMD:
Once project is up and running will post schedule for following street:
- Elizabeth Street
May 18, 2026, Update:
No changes from last week.
May 11, 2026, Update:
Gary-New Duluth:
Storm Work will start week of 11th along with concrete removals (concrete curb and gutter and driveways):
- Gary Street
- West Dickson Street
- Hudson Boulevard
Duluth Heights:
The watermain replacement project will be completed by end of June and then street work will begin:
- Chambersburg Avenue
Kenwood:
Once project is up and running will post schedule for following streets:
- East 13th Street
- Fern Avenue
- Martha Street
- Howtz Avenue
- Cliff Avenue
- Hawkins Street
- Boulevard Place
Chester Park-UMD:
Once project is up and running will post schedule for following street:
- Elizabeth Street


