Engineering

2024 Sales Tax Projects

The proposed project will involve one of the following on each street (see list of streets here):

  • Reclamation and paving – (1) Milling 2-3 inches of bituminous off street. (2) Reclaim the street which involves grinding up remaining pavement and 2-3 inches of subgrade (gravel) and then, (3) paving 3-4 inches of new pavement.
  • Mill and overlay – Milling 1.5-2 inches of paving off street and paving a new 1.5-2 inches layer of paving.

In addition to the street work, there will be some stormwater infrastructure repairs as well as ADA upgrades where possible, mostly at pedestrian ramps at intersections. Some residential and business driveways will require concrete work. Notice will be given to individual residents when access will be limited, usually about a week, by the contractor. The project should not affect mail delivery or garbage pickup schedules. It is advisable to put your house number on your garbage cans in case they get moved so we can get them back to you. Streets will be temporarily posted “No Parking” on multiple occasions during the project. Signs will be removed when you can park and reposted when necessary, such as for milling and then again for paving.
The City of Duluth’s Streets Sales tax will fund these projects and there will be no assessments for the projects to property owners.

Common questions and answers:

  • Will garbage still be picked up?
    • Yes, garbage pickup will still occur.
  • Can I still access my driveway?
    • Most of the time, yes.  The only time this will be affected is if there needs to be driveway concrete work performed.  If there needs to be driveway concrete replacement, we will knock on doors and notify property owners. 

If you would like more information about when your street is scheduled for improvement, please keep visiting this website for more weekly status updates.


Current status updates:

Week of July 15th, 2024

The Project is about 3 weeks behind due to the recent rain events. Below is the current schedule for the next few weeks.

Paving is completed. Miscellaneous concrete work, cleanup, topsoil, seed and blanket behind curb this week on these streets.

  • W 5th Street
  • W 4th Street
  • N 39th Ave W
  • N 38th Ave W
  • N 41st Ave W
  • N 57th Ave W
  • N 56th Ave W
  • Spirit Dr
  • 57th Ave W

Concrete work should be completed this week. Milling scheduled for week of 22nd. Paving week of 29th on these streets:

  • W 6th Street
  • W 5th Street (Skyline)
  • Lake Ave

Storm sewer finishing this week, concrete removals and preparing road for paving. Paving won’t happen till August.

  • E 7th Street (from 13th to 14th)

Concrete work starting week 22nd on these streets:

  • Como Ave
  • E Gilead Ave
  • E Locust Street
  • Myrtle Pl
  • Myrtle Street

Removals and concrete work continuing this week on following streets:

  • E 5th Street
  • E 6th Street
  • E 7th Street
  • 16th Ave E

Saw cutting this week. Removals and concrete work the week of July 22nd:

  • E 9th Street
  • Garden Street

Pipework and saw cutting this week on following streets:

  • Water Street
  • 131st Ave

 

Saw cutting, lowering manholes this week on following streets:

  • Main Street
  • 80th Ave
  • 81st Ave
  • 84th Ave

This is the plan at this point. As the work progresses, the starting dates may change and will be updated on this website.

Milling and paving of the street will be scheduled at a later date and the streets will be reposted for each of those operations again.

We will try to maintain access unless we are pouring your driveway, at which point we will knock on your door and work with you as we will need about a week for concrete work.