Sales Tax Projects- Previous Status Updates

New concrete pouring, will be finished and Milling and Paving is scheduled for week of June 3rd.

  • N 57th Ave W
  • N 56th Ave W
  • Spirit Dr
  • 57th Ave W

Concrete pouring, will be finishing and Milling and Paving is scheduled for week of June 3rd.

  • W 5th Street
  • W 4th Street
  • N 39th Ave W
  • N 38th Ave W
  • N 41st Ave W

These streets were posted “No Parking” on May 20th with concrete sidewalk, curb, and catch basin removal occurring the week of the 20th. Concrete work will star week of May 27th.

Lake Ave. is the exception because of steep grades and removals will happen closer to concrete work.

  • W 6th Street
  • W 5th Street (Skyline)
  • N Lake Ave
  • W Myrtle Street

These streets were posted “No Parking” on May 20th with concrete sidewalk, curb, and catch basin removal. Driveway culvert replacement will be starting the week of June 3rd.

  • Como Ave
  • E Gilead Ave
  • E Locust Street
  • Myrtle Pl

This is the plan at this point. As the work progresses, the starting dates may change and will be updated on this website.

Milling and paving of the street will be scheduled at a later date and the streets will be reposted for each of those operations again.

We will try to maintain access unless we are pouring your driveway, at which point we will knock on your door and work with you as we will need about a week for concrete work.


Week of June 2, 2024

These streets are planned to be posted “No Parking” on the 2nd with concrete sidewalk, curb, and catch basin removal, and new concrete being poured:

  • Como Ave
  • E Gilead Ave
  • E Locust Street
  • Myrtle Pl
  • W Myrtle St

Week of May 19, 2024

These streets are planned to be posted “No Parking” on the 20th with concrete sidewalk, curb, and catch basin removal, and new concrete being poured.

  • W 13th Street
  • W 12th Street
  • N 22nd Ave W
  • W 6th Street
  • W 5th Street (Skyline)
  • N Lake Ave

Week of April 28, 2024

These streets were posted “No Parking”, and concrete sidewalk, curb, and catch basin removals, and new concrete pouring, has started.

  • N 57th Ave W
  • N 56th Ave W
  • Spirit Dr
  • 57th Ave W
  • W 5th Street
  • W 4th Street
  • N 39th Ave W
  • N 38th Ave W
  • N 41st Ave W

This process will take about two weeks on each street and then the “No Parking” signs will come down.


4/18/2024:

There were two informational sessions in May on the 2024 Duluth Street Projects.

One virtual public informational session:
Thursday, May 2nd, 2024
Location: Virtual
Time: Noon – 1:00 PM

Recording is in two parts because of the file size:

Part 1

Part 2


One in-person public informational session:
Thursday, May 2nd, 2024
Location: Downtown Duluth Public Library, 520 W Superior St., Duluth, MN, 55802
Time: 5:30 PM - 6:30 PM