Week of June 30, 2025:
Morgan Park:
These streets were posted “No Parking” the week of May 19th with saw cutting, removal of sidewalk, curb, and catch basins starting the week of May 26th. Removals will continue until Morgan Park streets are completed.
Concrete forming starts May 29th and pouring concrete will start the week of June 2nd.
Milling and paving tentatively planned for the week of July 14th.
• Falcon Street
• 86th Ave W
• Edward Street
Utility locates and removals marking has been done. Removals, concrete and storm work are planned for the week of July 21st. Milling and paving will be scheduled after that for:
• Clyde Ave
Irving:
Sawcutting is completed. Removals and storm work have been delayed waiting for storm structures and rescheduled for the week of July 21st.
• 57th Ave. West
Lincoln Park:
Lincoln Park
Sawcutting is completed. Removals have been delayed waiting for storm structures and rescheduled for the week of July 28th.
• 1st Street Alley
Kenwood:
Sawcutting started week of May 26th, completed week of June 2nd. Removals tentatively scheduled week of July 7th.
• Cliff Avenue
• Plum Street
• High Street
• Triggs Avenue
• Baylis Street
Duluth Heights:
Sawcutting tentatively scheduled week of June 16th with removals scheduled for week of June 23rd.
• Anderson Road
To be scheduled:
• Maple Grove Road
• Stanford Avenue
• W Olive Street
• Observation Road
Piedmont Heights:
To be scheduled.
• Berkley Road
• Palisade Drive
• Parkwood Lane
• Portage Drive
• Portage Circle
• Karl Avenue
• Asbury Drive
• Echo Lane
• Palisade Circle
• Talmadge Circle
• Wildberry Lane
• Silver Fox Circle
• Twin Creeks Circle
• Hanford Avenue
Endion:
To be scheduled.
- London Road (see Planning Dept page for more information)
Week of June 23, 2025:
There are no changes from the previous week.
Week of June 16, 2025:
Morgan Park:
These streets were posted “No Parking” the week of May 19th with saw cutting, removal of sidewalk, curb, and catch basins starting the week of May 26th. Removals will continue until Morgan Park streets are completed.
Concrete forming starts May 29th and pouring concrete will start the week of June 2nd.
Milling and paving tentatively planned for the week of June 23rd.
- Falcon Street
- 86th Ave W
- Edward Street
Utility locates and removals marking has been done. Removals, concrete, and storm work are planned for the week of June 30th. Milling and paving will be scheduled after that for:
- Clyde Ave
Irving:
Sawcutting is completed. Removals and storm work have been delayed waiting for storm structures and rescheduled for the week of June 30th.
- 57th Ave. West
Lincoln Park:
Sawcutting is completed. Removals have been delayed waiting for storm structures and rescheduled for the week of June 30th.
- 1st Street Alley
Kenwood:
Sawcutting started week of May 26th, completed week of June 2nd. Removals tentatively scheduled week of July 7th.
- Cliff Avenue
- Plum Street
- High Street
- Triggs Avenue
- Baylis Street
Duluth Heights:
Sawcutting tentatively scheduled week of June 16th with removals scheduled for week of June 23rd.
- Anderson Road
To be scheduled:
- Maple Grove Road
- Stanford Avenue
- W Olive Street
- Observation Road
Piedmont Heights:
To be scheduled.
- Berkley Road
- Palisade Drive
- Parkwood Lane
- Portage Drive
- Portage Circle
- Karl Avenue
- Asbury Drive
- Echo Lane
- Palisade Circle
- Talmadge Circle
- Wildberry Lane
- Silver Fox Circle
- Twin Creeks Circle
- Hanford Avenue
Endion:
To be scheduled.
- London Road (see Planning Dept page for more information)
Week of June 9, 2025:
Morgan Park:
These streets were posted “No Parking” the week of May 19th with saw cutting, removal of sidewalk, curb, and catch basins starting the week of May 26th. Removals will continue until Morgan Park streets are completed.
Concrete forming starts May 29th and pouring concrete will start the week of June 2nd.
Milling and paving tentatively planned for the week of June 23rd.
- Falcon Street
- 86th Ave W
- Edward Street
Utility locates and removals marking has been done. Removals, concrete and storm work are planned the week of June 16th. Milling and paving week of June 23rd.
- Clyde Ave
Irving:
Sawcutting and removals scheduled for the week of June 23rd.
- 57th Ave. West
Lincoln Park:
Sawcutting and removals scheduled for the week of June 23rd.
- 1st Street Alley
Kenwood:
Sawcutting started week of May 26th, completed week of June 2nd. Removals tentatively scheduled week of June 7th.
- Cliff Avenue
- Plum Street
- High Street
- Triggs Avenue
- Baylis Street
Duluth Heights:
Sawcutting and removals tentatively scheduled week of June 14th.
- Anderson Road
- Maple Grove Road
- Stanford Avenue
- W Olive Street
- Observation Road
Piedmont Heights:
To be scheduled.
- Berkley Road
- Palisade Drive
- Parkwood Lane
- Portage Drive
- Portage Circle
- Karl Avenue
- Asbury Drive
- Echo Lane
- Palisade Circle
- Talmadge Circle
- Wildberry Lane
- Silver Fox Circle
- Twin Creeks Circle
- Hanford Avenue
Endion:
To be scheduled.
- London Road (see Planning Dept page for more information)
Week of June 2, 2025:
Morgan Park:
These streets were posted “No Parking” the week of May 19th with saw cutting, removal of sidewalk, curb, and catch basins starting the week of May 26th. Removals will continue until Morgan Park streets are completed.
Concrete forming starts May 29th and pouring concrete will start the week of June 2nd.
Milling and paving tentatively planned for week of June 23rd.
- Falcon Street
- 86th Ave W
- Edward Street
Utility locates and removals marking has been done. Removals planned the week of June 16th.
- Clyde Ave
Irving:
Sawcutting and removals scheduled for the week of June 23rd.
- 57th Ave. West
Piedmont Heights:
To be scheduled.
- Berkley Road
- Palisade Drive
- Parkwood Lane
- Portage Drive
- Portage Circle
- Karl Avenue
- Asbury Drive
- Echo Lane
- Palisade Circle
- Talmadge Circle
- Wildberry Lane
- Silver Fox Circle
- Twin Creeks Circle
- Hanford Avenue
Duluth Heights:
To be scheduled.
- Anderson Road
- Maple Grove Road
- Stanford Avenue
- W Olive Street
- Observation Road
Lincoln Park:
To be scheduled.
- 1st Street Alley
Kenwood:
Sawcutting started week of May 26th, to be completed week of June 2nd.
- Cliff Avenue
- Plum Street
- High Street
- Triggs Avenue
- Baylis Street
Endion:
To be scheduled.
- London Road (see Planning Dept page for more information)
Week of May 26, 2025:
Morgan Park:
These streets were posted “No Parking” the week of May 19th with saw cutting, removal of sidewalk, curb, and catch basins work will start the week of May 26th:
• Falcon Street
• 86th Ave W
• Edward Street
Utility locates and removals marking has been done on:
• Clyde Ave
Irving:
To be scheduled:
• 57th Ave. West
Piedmont Heights:
To be scheduled:
• Berkley Road
• Palisade Drive
• Parkwood Lane
• Portage Drive
• Portage Circle
• Karl Avenue
• Asbury Drive
• Echo Lane
• Palisade Circle
• Talmadge Circle
• Wildberry Lane
• Silver Fox Circle
• Twin Creeks Circle
• Hanford Avenue
Duluth Heights:
To be scheduled.
• Anderson Road
• Maple Grove Road
• Stanford Avenue
• W Olive Street
• Observation Road
Lincoln Park:
To be scheduled:
• 1st Street Alley
Kenwood:
To be scheduled:
• Cliff Avenue
• Plum Street
• High Street
• Triggs Avenue
• Baylis Street
Endion:
To be scheduled:
• London Road (see Planning Dept page for more information)