2025 Sales Tax Projects- Updates

2025 Street Preservation Project-general comments on work schedule:

We will try to maintain mail and garbage service.

We will try to maintain access unless we are pouring your driveway, at which point we will knock on your door and work with you as we will need to allow about a week to pour your driveway and allow for curing before you can drive on it.

Some streets need storm work and might have short-term closures.

Milling and paving the street will be scheduled once a group of streets have the concrete work completed. The streets will be reposted “No Parking” for each of those operations again.


Week of November 10, 2025:

Irving:

Restoration work is expected to occur this week.

  • 57th Ave. West

Piedmont Heights:

Restoration work is expected to occur this week. Manhole and valve collars will resume next week.

•    Berkley Road
•    Palisade Drive
•    Parkwood Lane
•    Portage Drive
•    Portage Circle
•    Karl Avenue
•    Asbury Drive
•    Echo Lane
•    Palisade Circle
•    Talmadge Circle
•    Wildberry Lane
•    Silver Fox Circle
•    Twin Creeks Circle
•    Hanford Avenue

Endion:

Restoration work is expected to occur this week.

  • London Road

 Click this link to see past/archived updates.