2025 Sales Tax Projects- Updates
2025 Street Preservation Project-general comments on work schedule:
We will try to maintain mail and garbage service.
We will try to maintain access unless we are pouring your driveway, at which point we will knock on your door and work with you as we will need to allow about a week to pour your driveway and allow for curing before you can drive on it.
Some streets need storm work and might have short-term closures.
Milling and paving the street will be scheduled once a group of streets have the concrete work completed. The streets will be reposted “No Parking” for each of those operations again.
Week of August 25, 2025:
Morgan Park:
These streets were posted “No Parking” the week of May 19th with saw cutting, removal of sidewalk, curb, and catch basins starting the week of May 26th. Removals will continue until Morgan Park streets are completed
Concrete, milling, paving and restoration work is complete.
Minor cleanup in the coming weeks.
• Falcon Street
• 86th Ave W
• Edward Street
Utility locates and removals marking has been done. Removals, concrete and storm work have been delayed until the week of September 15th. Milling and paving will be scheduled after that for:
• Clyde Ave
Irving:
Sawcutting is completed. Removals and storm work have been delayed waiting for storm structures and rescheduled for the week of September 22nd.
• 57th Ave. West
Lincoln Park:
Sawcutting is completed. Removals have been delayed waiting for storm structures and rescheduled for the week of September 29th.
• 1st Street Alley
Kenwood:
Removals will continue the week of Aug 25th. Concrete work on curbs and driveways will continue onto Cliff Ave., the rest of High and Plum the week of August 25th also. Reclaim will start week of August 25th with paving following.
• Cliff Avenue
• Plum Street
• High Street
• Triggs Avenue
• Baylis Street
Duluth Heights:
Concrete and storm work is completed. Milling completed the week of August 18th. Paving scheduled to start Friday, August 22nd and continue week of August 25th.
• Anderson Road
To be scheduled:
• Maple Grove Road - possible milling week of August 25th.
• Stanford Avenue
• W Olive Street
• Observation Road
Piedmont Heights:
Manholes are lowered, concrete removals starting week of Aug 11th and continue week of August 25th, concrete work and perforated pipe for drainage will start week of August 25th.
• Berkley Road
• Palisade Drive
• Parkwood Lane
• Portage Drive
• Portage Circle
• Karl Avenue
• Asbury Drive
• Echo Lane
• Palisade Circle
• Talmadge Circle
• Wildberry Lane
• Silver Fox Circle
• Twin Creeks Circle
• Hanford Avenue
Endion:
Some structure work and concrete work starting the week of September 2nd.
- London Road