2024 Sales Tax Projects - Current Updates

The 2024 Sales Tax Street Project will involve one of the following on each street (see list of streets here):

  • Reclamation and paving – (1) Milling 2-3 inches of bituminous off street. (2) Reclaim the street which involves grinding up remaining pavement and 2-3 inches of subgrade (gravel) and then, (3) paving 3-4 inches of new pavement.
  • Mill and overlay – Milling 1.5-2 inches of paving off street and paving a new 1.5-2 inches layer of paving.

In addition to the street work, there will be some stormwater infrastructure repairs as well as ADA upgrades where possible, mostly at pedestrian ramps at intersections. Some residential and business driveways will require concrete work. Notice will be given to individual residents when access will be limited, usually about a week, by the contractor. The project should not affect mail delivery or garbage pickup schedules. It is advisable to put your house number on your garbage cans in case they get moved so we can get them back to you. Streets will be temporarily posted “No Parking” on multiple occasions during the project. Signs will be removed when you can park and reposted when necessary, such as for milling and then again for paving.
The City of Duluth’s Streets Sales tax will fund these projects and there will be no assessments for the projects to property owners.

Common questions and answers:

  • Will garbage still be picked up?
    • Yes, garbage pickup will still occur.
  • Can I still access my driveway?
    • Most of the time, yes.  The only time this will be affected is if there needs to be driveway concrete work performed.  If there needs to be driveway concrete replacement, we will knock on doors and notify property owners. 

If you would like more information about when your street is scheduled for improvement, please keep visiting this website for more weekly status updates.


Current status updates:

Week of September 23th, 2024

Below is the current schedule for September 2024.

Fond-Du-Lac

These streets are paved.  Mr. Manholes and punch list items remain.  

  • Water Street
  • 131st Ave

Norton Park

Concrete work is 95% complete.  Milling is 100% complete.  Paving to start week of 9/30

  • 80th Ave West
  • 81st Ave West
  • 84th Ave West

Bayview Heights

Concrete work is 90% complete.  Storm work is 100% complete.  Final paving scheduled for the week of 9/30.

  • Brook Street
  • Lawn Street
  • Meadow Street
  • Vinland Street Alley (storm work on alley will start 1st week of September after gas main work completed, paving after Alley storm)

Fairmount

Work is complete.  Punchlist items to be addressed in October.

  • Main Street

Spirit Valley

These Streets are complete other than Punchlist items.

  • 56th Ave West
  • 57th Ave West
  • Spirit Drive

Denfeld

These Streets are complete other than manhole treatments in street and Punchlist items.

  • 38th Ave West
  • 39th Ave West
  • 41st Ave East
  • W 4th Street
  • W 5th Street

Lincoln Park

These streets have been removed from project for this year. Lead service replacement will happen and then these streets will be added to 2025 or 2026 Street Preservation. Letters will be sent to property owners:

  • W 11th Street
  • W 12th Street
  • W 13th Street
  • 22nd Ave West

Duluth Heights

These streets are complete other than manhole treatments in street and punch list items:

  • Como Ave
  • E Gilead Ave
  • E Locust Street
  • Myrtle Street

Reclaim and paving scheduled for the end of week of 9/23:

  • Myrtle Place

Central Hillside

These streets are complete other than manhole treatments in street and punch list items:

  • N Lake Ave
  • W 5th Street from Skylie
  • W 6th Street

East Hillside

Concrete work is 95% complete.  Milling is 100% complete.  Paving beginning 9/21:

  • 8th Ave East
  • 11th Ave East
  • 14th Ave East
  • Belmont road
  • Parkland Ave
  • Chester Parkway
  • E 7th Street
  • East 10th Street
  • Eden Lane

Storm sewer complete. Private Lead service work completed. Concrete work complete.  Paving scheduled for week of 9/23

  • E 7th Street (from 13th to 14th)

Endion

Concrete work is 95% complete.  Milling is 100% complete.  Paving beginning 9/21:

  • 16th Ave East
  • 17th Ave East
  • E 5th Street
  • E 6th Street
  • E 7th Street

Chester Park

Concrete work is 98% complete.  Milling is 100% complete.  Paving beginning 9/21:

  • E 9th Street
  • Garden Street (storm work week of 26th also)

Hunters Park

Storm work is complete.  Concrete work is 75% complete.  Milling to begin week of 9/30. Paving to begin week of 9/30.

  • Vermillion Road
  • Woodhaven Lane
  • Hartley Road

Congdon Park

Concrete work complete.  Reclaim to begin on 9/27.  Paving beginning week of 9/30

  • Crescent View Ave
  • Rustwood Lane (storm work week of August 26th)
  • Old Howard Mill Road

Lakeside-Lester Park

Removals are 90% complete.  Concrete work to begin week of 9/23.  Milling to begin week of 9/30.  Paving begins week of 10/7:

  • 51st Ave East
  • 52nd Ave East
  • Crosley Ave. (storm work starting week of August 26th)
  • Idlewild Street
  • Covent Place
  • Kingston Street
  • Norwood Street
  • Oneida Street

This is the plan at this point, weather permitting. As the work progresses, the starting dates may change and will be updated on this website.

When milling and paving of the street occurs the streets will be reposted for each of those operations again.

We will try to maintain access unless we are pouring your driveway, at which point we will knock on your door and work with you as we will need about a week for concrete work.