DATE: 10/19/2026
SUBJECT: West Superior Street reconstruction project update for week ending October 16, 2026
BY: Kelli Latuska, Public Information Officer
SUBJECT: West Superior Street reconstruction project update for week ending October 16, 2026
BY: Kelli Latuska, Public Information Officer
West Superior Street reconstruction project update for week ending October 16, 2026
Work completed this week
- Continued placing new roadway base west of Garfield Avenue.
- Completed sidewalk east of Garfield Avenue and continued trail construction.
- Continued work on conduit and light bases for street lighting and traffic signals.
- Completed storm sewer construction west of the Garfield Avenue intersection.
- Continued placing new roadway base in the 27th Avenue W intersection.
- Prepared reinforcing steel for bus shelter foundations at Garfield Avenue.
- Began placing topsoil in completed area.
Anticipated work scheduled for next week
- Complete concrete pours from Michigan Street to Garfield Avenue.
- Continue light base installations.
- Continue placing topsoil.
- Continue constructing road base west of Garfield Avenue.
- Pour concrete for bus shelter foundations at Garfield Avenue.
- Continue constructing road base in the 27th Avenue W intersection.
- Begin curb and gutter placement east of Garfield Avenue and in the 27th Avenue W intersection.
- Lower gas main along west side of 18th Avenue W from First Street to Michigan Street.
Expected impacts from next week’s work
- Additional closed area along west side of 18th Avenue W from First Street to Michigan Street.
Closed areas
- W Superior Street from west of 18th Avenue W to Michigan Street except for access to 16th Avenue W. Garfield Avenue and Piedmont Avenue across W Superior Street is also open.
- 27th Avenue W and W Superior Street at the intersection.
Detour routes
- Vehicle traffic:
- W Superior Street traffic is detoured along W Michigan Street/Lower Michigan Street to 21st Avenue W. Both directions will return to this route following MnDOT reopening access to downtown from W Michigan Street.
- W Superior Street is detoured at Carlton Street onto W Michigan Street to 24th Avenue W.
- 27th Avenue W is detoured at W Michigan Street onto 24th Avenue W to West 1st Street.
- Cross City Trail users: Cross City Trail is detoured at 28th Avenue W onto West First Street to 26th Avenue W.
Access to businesses
- M&H Gas Station: Access is along the detour route.
- Duluth Gospel Tabernacle: Access via Garfield Avenue or Piedmont Avenue to 16th Avenue W.
- Businesses in the 1700 block of West Superior Street: Pedestrian access will be maintained from the west end of the project.