DATE: 8/14/2026
SUBJECT: West Superior Street reconstruction project update for August 14, 2026
BY: Kelli Latuska, Public Information Officer
SUBJECT: West Superior Street reconstruction project update for August 14, 2026
BY: Kelli Latuska, Public Information Officer
West Superior Street reconstruction project update for August 14, 2026
Work completed this week
- Reopened W Michigan Street at the intersection with Superior Street.
- Completed storm sewer construction in the Garfield Avenue intersection.
- Completed a temporary surface in the Garfield Avenue intersection for Port traffic and access to 16th Avenue W.
- Completed removals east of Garfield Avenue.
- Began traffic signal base installation and placed conduit in the Garfield Avenue intersection.
- Began grading for sidewalk and curb and gutter in the Garfield Avenue intersection.
Anticipated work scheduled for next week
- Complete curb and gutter in the Garfield Avenue intersection.
- Complete storm sewer construction east of the Garfield Avenue intersection.
- Begin grading the roadway and sidewalk between Garfield Avenue and W Michigan Street.
- Mill the existing asphalt roadway between 18th Avenue W and Garfield Avenue.
- Begin storm sewer construction west of the Garfield Avenue intersection.
Expected impacts from next week’s work
- The Contractor will continue to coordinate with the Garfield Square Apartments and Duluth Gospel Tabernacle for access through the closure to 16th Avenue W.
- Milling will remove access through the 18th Avenue W intersection with W Superior Street.
Closed areas
- W Superior Street from west of 18th Avenue W to Michigan Street except for access to 16th Avenue W
Detour routes
- Vehicle traffic: W Superior Street traffic is detoured at 21st Avenue W onto W Michigan Street/Lower Michigan Street. Piedmont Avenue and Garfield Avenue are detoured onto Railroad Street to Fifth Avenue W to West First Street.
- Cross City Trail users: No detour route, Cross City Trail is complete through the project area.
Access to businesses
- M&H Gas Station: Access is along the detour route.
- Duluth Gospel Tabernacle: Access via Garfield Avenue to 16th Avenue W until notified that it will switch to access via Piedmont Avenue to 16th Avenue W.
- Businesses in the 1700 block of West Superior Street: Pedestrian access will be maintained from the west end of the project.