West Superior Street Update
411 West First Street • Duluth, Minnesota 55802
218-730-5309 • www.westsuperiorstreet.org
218-730-5309 • www.westsuperiorstreet.org
For more information contact Alex Popp,
Project Engineer at 218-730-5087, apopp@DuluthMN.gov
or Kelli Latuska, Public Information Officer at 218-730-5309
Project Engineer at 218-730-5087, apopp@DuluthMN.gov
or Kelli Latuska, Public Information Officer at 218-730-5309
DATE: 7/24/2026
SUBJECT: West Superior Street reconstruction project update for week of July 24, 2026
BY: Kelli Latuska, Public Information Officer
SUBJECT: West Superior Street reconstruction project update for week of July 24, 2026
BY: Kelli Latuska, Public Information Officer
West Superior Street reconstruction project update for week of July 24, 2026
Work completed this week
- Continued reconnecting water services east of Garfield Avenue to new water main.
- Blasted rock for storm sewer trenches and began excavation.
- Poured median curb and curb on the north side of W Michigan Street.
- Reconnected water services east of Garfield Avenue to new water main.
- Continued electrical work along W Michigan Street.
- Milled asphalt pavement in the Garfield Avenue/Piedmont Avenue intersection with W Superior Street.
Anticipated work scheduled for next week
- Pave W Michigan Street and the Cross City Trail.
- Construct the foundation for the welcome monument sign.
- Remove pavement, construct water main and storm sewer, and grade surface in the Garfield Avenue/Piedmont Avenue intersection with W Superior Street.
- Continue rock removal along storm sewer runs on W Superior Street.
Expected impacts from next week’s work
- Work in the Garfield Avenue/Piedmont Avenue intersection with W Superior Street will close that intersection beginning July 27.
- The Contractor will coordinate with Garfield Square Apartments and Duluth Gospel Tabernacle for access through the closure.
Closed areas
- W Michigan Street at W Superior Street.
- W Superior Street from 225 feet east of 18th Avenue W to Michigan Street except for access to 16th Avenue W.
Detour routes
- Vehicle traffic: Detoured at 21st Avenue W and Fifth Avenue W onto West First Street. Piedmont Avenue and Garfield Avenue are detoured onto Railroad Street to Fifth Avenue W and along the previously existing detour.
- Cross City Trail users: No detour route; a section of the trail is on a gravel surface and will be directed through the construction zone when paving is taking place.
Access to businesses
- M&H Gas Station: Access from the east side of the project via West Superior Street or Glen Place.
- Duluth Gospel Tabernacle: Access via Piedmont Avenue to 16th Avenue W until approximately midweek at which time access will be via Garfield Avenue to 16th Avenue W.
- Businesses in the 1700 block of West Superior Street: Access from the west side of the project.